How Long Modon Takes to Build

Facts read · Sources at the end of the page

A finished Nawayef East Home from its garden and pool
A finished Nawayef East Home from its garden and pool. Modon's render of the earlier Nawayef hills, not of Nawayef South.

Modon's Hudayriyat Island communities are scheduled for handover 39 to 57 months after their launch, with a median of 49 months, by our arithmetic on Modon's own dates read on Nov 13, 2026. These are schedules, not a track record: we found no Modon release announcing a completed handover of homes on the island. Applied to a December 2026 launch, the same spans would put Nawayef South's handover between March 2030 and September 2031, which is our arithmetic and not a forecast by Modon.

Next: the cash due at the start of that wait, the income needed to finance the payment due at handover or how Nawayef compares with Wadeem Gardens, the island's longest wait.

Launch to scheduled handover, launch by launch

Launch dates are the dates of Modon's press releases. Handovers are from each community's page on modon.com, or from the Hudayriyat Island page where a community page gives none. Where Modon names a quarter we count to its last month. The months are our arithmetic.

Community Launched Scheduled handover Months between
Nawayef Park Views (apartments) Dec 10, 2024 Q1 2028 39
Nawayef Village (townhouses) May 6, 2025 From Q1 2029 46
Bashayer, final phase (apartments, townhomes) Mid-July 2026 Q2 2030 47
Nawayef East (villas, mansions) Nov 7, 2024 December 2028 49
Hudayriyat Golf Estates Early July 2026 "By August 2030" 49
Bashayer, villas Dec 8, 2025 Q1 2030 51
Bashayer, first apartments Dec 8, 2025 Q2 2030 54
Wadeem Gardens (villas) Sep 30, 2026 "By Q2 2031" 57
Shortest 39 months, Nawayef Park Views
Longest 57 months, Wadeem Gardens
Median of the eight 49 months

Villas take longer than apartments in this list: the rows that are villas (Nawayef East, Bashayer's villas, Wadeem Gardens) run 49, 51 and 57 months.

Notes on the dates

  • Hudayriyat Golf Estates. Modon's release of Jul 7, 2026 reports sales "within days of launch" without giving the launch day, so we count from July 2026.
  • Bashayer. Modon's pages disagree. The Bashayer page says villas in Q1 2030 and apartments in Q2 2030; the island page's card says Q1 2029 and its FAQ says "Q3 2028". We used the community's own page. On the island page's Q1 2029, Bashayer would be 39 months.
  • Al Naseem Community. Its page schedules the first phase for Q4 2027, while the island page's FAQ says Q4 2026. Modon's media center has no launch release for it, so it has no row.
  • Wadeem. The plots community launched on Jul 1, 2025 is land for owners to build on; the release gives no handover date.
  • Nawayef West. No launch release and no handover date on modon.com.

Has Modon handed over any home on the island?

Not by anything Modon has published. Its media center, read Nov 13, 2026, holds launch, sell-out and contract releases for Hudayriyat Island and none announcing a handover. The earliest date on its pages is Al Naseem's, and Modon's own two pages put that in either Q4 2026 or Q4 2027. Its first-half results of Jul 29, 2026 speak of progress that is "expected to accelerate project handovers", in the future tense.

The one construction milestone on record for the hills is the main contract for Nawayef East and Nawayef West, awarded on Dec 19, 2025, 13 months after the east hill's launch and 36 months before its scheduled handover. The viki follows that contract on its handover page.

What the same spans would mean for Nawayef South

Modon told the broker Emigeo that Nawayef South launches in December 2026. Modon has published no handover date for it. Counting from December 2026:

If it took as long as Months Handover would fall in
The shortest, Nawayef Park Views 39 March 2030
Nawayef East, also the median 49 January 2031
The longest, Wadeem Gardens 57 September 2031

This is our arithmetic, not a forecast by Modon. We think the villa rows are the fairer guide for a hill of villas, which points to 2031 more than 2030. On a plan like the east hill's 40/60, the handover month is also when the largest payment falls due.

To hear Nawayef South's prices and handover date on launch day, register on the home page.